Library move pressured by foundation schedule; select board approves advertising for Clerk of the Works
Summary
The library project faces a tight schedule: the structure move is set for April 19 and the foundation must be poured within 45 days, or daily fees could apply. The board agreed to advertise for a clerk of the works, solicit hourly rates, and to put concrete foundations out to bid promptly to avoid schedule risk.
Get email alerts on the Community Facilities topic
No spam. Unsubscribe anytime.
Town staff updated the board on the library rehabilitation: the historic brick front will become a flexible community space and the building move is scheduled for the weekend of April 19. Staff warned that the foundation needs to be poured within 45 days after the move to avoid daily fees and urged immediate procurement action. ‘‘If we don’t have a plan… then we could roll the building into a hole and have no idea when you can pull the steel out,’’ staff said, urging the board to put the concrete package out to bid forthwith.
To support the project, the board moved to advertise a Clerk of the Works position to oversee construction for the library job, asking for hourly-rate proposals rather than a fixed cap and to list the opportunity on the state registry and bid platforms. Members discussed targeted outreach (VLCT registry) and supplemental advertising; the motion to advertise passed by voice vote. Staff also said they will pursue geotechnical or conservative foundation plans with structural engineers to keep the schedule while managing cost and risk.