Commission approves change order for Justice Center roofing repairs

Cass County Commission · July 24, 2026

Summary

Cass County approved Change Order No. 001 with Delta Innovative Services Inc. for roofing repairs at the Justice Center after maintenance staff reported peeling roofing and water intrusion around vestibules; the measure passed 3–0.

The commission approved Resolution 26-71 to authorize Change Order No. 001 with Delta Innovative Services Incorporated for additional roofing work at the Cass County Justice Center.

Bobby, maintenance staff, described the problem area as the outer areas above the two front vestibules for the sheriff's and court areas and one area at the back. "The old roofing has been peeling up and rolled up. So water is allowed to get through there," he said. The contractor will remove affected material and apply double layers and a stony application consistent with other roofing on the complex.

The motion was moved, seconded and approved unanimously (3–0). The transcript did not include a dollar figure for the change order; staff indicated the work matches the scope used elsewhere on the complex.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source