Council approves $262,530 pay application to Industrial Process Technologies for WWTP construction
Summary
The council approved pay application No. 15 from Industrial Process Technologies for $262,530 for construction work on the wastewater treatment plant (WWTP) through July 20, 2024. Staff noted work included aeration, equipment installation and piping.
Get email alerts on the Wastewater topic
No spam. Unsubscribe anytime.
The Alcester City Council approved payment of pay application No. 15 from Industrial Process Technologies (IPT) for $262,530 for construction work on the wastewater treatment plant through July 20, 2024.
Staff summarized that IPT had worked on aeration equipment installation, doors, painting, bump and pot (pipe) installation and associated tasks. A council member moved to approve the payment application and the motion carried by vote. Staff will process the payment and record it as part of the WWTP construction contract's pay schedule.