Council approves change order to extend sewer contract and pay storage, access work

Alcester City Council · November 12, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Change Order #1 to the sanitary‑sewer cleaning and televising project to extend completion dates, reimburse storage for contractor's heated jet truck and add $1,700 to open a 10‑inch PVC line for future access.

Council considered and approved Change Order #1 to the sanitary sewer cleaning and televising contract. The change order extends the substantial completion date from Nov. 27 to Dec. 27 and moves final completion from Dec. 31 to Jan. 31 to account for contract delays and CCTV timing.

The presenter said the contractor needs to store a heated jet‑truck on cold nights and negotiated a storage arrangement at a local facility that will charge about $100 per night; the meeting estimated roughly 14 nights (about $1,400) though the final amount will be reconciled at project end. The presenter also explained a $1,700 allowance to cut the top off a 10‑inch PVC pipe to create a standard manhole opening so cleaning equipment can be inserted.

"That's why the total increased price is estimated to be $3,100," the presenter said, citing the storage and pipe‑access costs; the change order raises the contract from $89,702.40 to $92,802.40. A council member moved to approve the change order and the motion carried.