Alcester approves $31,303.83 change order for wastewater plant, contractor gives new total
Summary
Council approved Change Order No. 10, adding $31,303.83 to the wastewater treatment contract for variable frequency drives, a flow meter replacement, sump pumps and electrical relays, raising the reported contract total to $5,447,451.64.
Get email alerts on the Change Order Wastewater topic
No spam. Unsubscribe anytime.
Council approved Change Order No. 10 for the wastewater treatment facility project to address failing variable frequency drives (VFDs), a malfunctioning flow meter, sump pump outlets and missing electrical relays. Staff said the items were discovered after work began, and some equipment delivery delays could prompt future time-extension requests.
Staff summarized the cost impact: "So the total cost for these changes is $31,303.83, bringing the total contract price to $5,447,451.64." The council moved and approved the change order by voice vote. Staff cautioned that VFD delivery delays may require additional change orders for schedule extensions.