District reports progress on Harrison Avenue, Purchase and Preston school construction
Summary
Dr. Wold told the board that Harrison Avenue library demolition and foundation work is underway with trenching toward Union Avenue; Purchase School roof is partially on and expected to be closed up within two weeks; Preston School has half of its foundation in and demolition is complete.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Dr. Wold told the board the district is "making progress on all of our projects," detailing construction at multiple sites: Harrison Avenue (library removal, foundation work and trenching toward Union Avenue), Purchase School (roof partially on; expected to be closed up within two weeks) and Preston School (about half of its foundation complete and demolition finished).
Board members were given an update on timelines and visible construction activity. No contract disputes or budget figures were presented in the public update during this meeting; the finance and facilities consent agenda later included a deduct change order for the Harrison High baseball field but the administration did not provide the monetary amount during the public report.