Council approves generator project placement; estimated cost over $400,000 covered by grants

City Council of Ozawkie, Kansas · November 11, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved the generator project placement and noted CES could issue bidding documents before Jan. 1; the council reported the estimated cost is over $400,000 and that grants will fully cover the expense.

The council approved the proposed placement plan for a municipal generator and heard that CES could have bidding documents ready before Jan. 1 if the plan is approved. Meeting minutes state the estimated project cost is over $400,000 and is completely covered by grants.

Rob Fisher moved to approve the plan and Kevin Klenklen seconded; the motion passed unanimously. Council did not record additional funding obligations for the city in the minutes; next steps include finalizing bidding documents and coordinating grant‑funded procurement.