District outlines septic-field fix at transportation facility; work to finish in two months

McCall-Donnelly Joint School District Board · December 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Director Jason Clay told the board the transportation facility has a septic-field problem and presented a mitigation plan; the district expects the work to be completed within the next two months.

Director of Operations Jason Clay briefed the McCall-Donnelly Board on a septic-field problem at the district's transportation facility and described a mitigation plan. Clay told the board the corrective work is planned and estimated to be completed within the next two months.

The issue was presented as part of the Operations 5-Year Plan discussion; the board did not take separate formal action but adopted the broader capital improvement plan that lists transportation facility work among priorities. Staff were directed to include needed repairs in upcoming procurement and project scheduling.