Summary

Mayor Brian Sabo reported a pumphouse motor purchased in 1993 shorted out and a $37,500 replacement is budgeted for 2026 (an American-made alternative estimated at $27,000 may be quicker); the planner updated council on lift station #2 work and announced a Jan. 6 public hearing on the Cascade Business Park utilities.

Mayor Brian Sabo told the council that the pumphouse motor, originally purchased in 1993, shorted out recently and a replacement is budgeted at $37,500 from sewer/water reserves for 2026. He said the GE-type motor must be ordered from China and has about a 16-week lead time; staff reported an American-built motor could be obtained faster and is estimated at roughly $27,000.

Planner Richard updated the council on lift station #2 replacement work and said he is coordinating with the public works board and expects input from Jackson Civil Engineers. He also raised concerns about overlapping boundaries on the Cascade Renewable Transmission project and said the developer may request a council nominee to participate; staff announced a public hearing on Jan. 6 regarding the Cascade Business Park and utility extensions.

Council did not take formal action on the pumphouse motor at the Dec. 9 meeting beyond noting the budgeted replacement; further procurement and schedule decisions will be handled by staff.