River Ridge board ratifies $150,786 change order after debate over process
Summary
The board ratified an MRI Construction change order totaling $150,786.09 for Phase I/II stormwater work after supervisors debated whether spending the amount without a special meeting reflected a fiscal process problem.
Get email alerts on the Stormwater Management topic
No spam. Unsubscribe anytime.
The River Ridge Community Development District board voted unanimously to ratify MRI Construction, Inc. Change Order Estimate #500 for price changes to Phase I and Phase II stormwater management projects in the amount of $150,786.09. The motion, made by Kurt Blumenthal and seconded by Keith Merrill, was approved "with all in favor."
Terry Mountford criticized the decision, saying the CDD was already "$300,000+ over budget for this type of project" and calling approval of an additional $150,786.09 without a special meeting evidence of a "major dysfunction in the CDD’s operating process." Charlie Krebs and Eric Long explained that inlets were relocated and other field adjustments followed homeowner input and site conditions; Krebs said the altered bid specifications produced a product "that will function and meet the expectations for eliminating the standing water." Blumenthal noted timing and carryover concerns, explaining that roughly $500,000 in loan funds for the stormwater work were carried into FY2025 because the Seaside and Master projects completed later than planned.
The Board directed District Counsel Tony Pires to draft ground rules for handling situations when projects exceed specified amounts, including requirements around scheduling a special meeting or specifying a contingency approval threshold. The entry and ratification are recorded on the meeting minutes; the ratification motion appears in the official actions for this meeting.