Commission approves change orders and Pay Application #3R for waterline work
Summary
The commission carried motions to approve Change Orders #3 and #4 and to adopt Pay Application #3R to reconcile plan vs. actual quantities on a waterline project. City Administrator Robin Lucero noted the seeding, mulching and fertilizing quantities were higher than planned.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Lead City Commission approved two change orders and a revised pay application to reconcile plan quantities and actual work completed on a waterline project. Minutes state the seeding, mulching and fertilizing quantities were significantly higher than originally planned, prompting a pricing adjustment.
"This quantity adjustment justified a price reduction to this item," the minutes record. The commission carried the motions (M/Carr, S/Thomas for change orders; M/Carr, S/Klein for Pay App #3R). Robin Lucero told the commission that Pay App #3R will replace the Pay App #3 approved Sept. 2, 2025; the minutes show the commission carried the motion. No dollar amounts for the change orders were recorded in the meeting summary included in the minutes.