Road crew reports completion of Noyestar road project, culvert upgrades; maintenance continues
Summary
The road crew reported finishing the Noyestar road better-roads project and upgrading culverts with a rented excavator; ongoing work includes grading and adding gravel as needed.
Get email alerts on the Road Maintenance topic
No spam. Unsubscribe anytime.
The Walden road crew told the Selectboard on Aug. 11 that it had finished the Noyestar road better-roads project and upgraded culverts using a rented excavator. The minutes note that the crew is continuing routine maintenance, grading, and adding gravel as needed.
No dollar figures, contractor names beyond the rented equipment, or projected completion dates for remaining maintenance were recorded in the minutes. The road report as recorded focuses on completed capital work (project and culverts) and on near-term routine tasks.