Council approves $195,035 in change orders for 2025 sewer rehabilitation project
Summary
Midvale authorized two change orders with Noland & Son—$96,525 for a 165-foot replacement on Cottonwood Street and $99,510 for design changes at Wasatch/Main including added manholes and 170 feet of upsized pipe—raising the project running total to $3,142,226.
Get email alerts on the Sewer Infrastructure topic
No spam. Unsubscribe anytime.
Branden Anderson summarized change-order work for the 2025 Sewer Rehabilitation Project originally contracted with Noland & Son Construction Co. Inc. Staff identified a problematic section on Cottonwood Street requiring replacement of 165 feet of existing 8-inch sewer main at a cost of $96,525. Additional work at the Wasatch and Main intersection—designed to improve long-term durability and accommodate conflicts with stormwater piping and existing waterlines—adds $99,510 and includes removal and replacement of two manholes, addition of a third, and 170 feet of upsized sewer pipe.
The proposed change orders increased the running contract total to $3,142,226. Anderson said schedule remains the same with anticipated May 2026 completion; the council suspended the rules and approved Resolution No. 2026-R-18 authorizing the mayor to approve the change orders.