Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure topic

No spam. Unsubscribe anytime.

Hillsboro electric superintendent reports underground work, AMI rollout and delayed bucket truck

Hillsboro City Council · April 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Electric superintendent Todd Helmer told the council the department has focused on underground projects (Orchard Ridge, Grand Oaks Apartments), is preparing for AMI meter training, helped connect a planned solar farm, and expects a delayed bucket truck delivery in 2027.

Todd Helmer, supervisor of the electric department, gave a status update on ongoing and planned infrastructure work. He said crews have installed underground wiring and transformers at new duplex developments and rebuilt the system at Grand Oaks Apartments; the department is also preparing to energize a transformer at a Tabor College science building once wiring is completed.

Helmer said the department assisted with equipment to connect a planned solar farm to city lines, and staff will begin training on an advanced metering infrastructure (AMI) rollout next week. He also told council the large bucket truck the department ordered has been delayed and now is expected to arrive in early 2027. "If the lights are on, it's a good day," Helmer said, summarizing his team's priority to maintain reliable service.