Durand council approves $849,712.40 pay request for Madison Street project
Summary
The council approved McCabe Construction's pay request #3 for the Madison Street project totaling $849,712.40 on July 8; the vote was unanimous.
Get email alerts on the Street Infrastructure topic
No spam. Unsubscribe anytime.
The City of Durand approved pay request #3 from McCabe Construction for the Madison Street project in the amount of $849,712.40. Council Member Matt Roesler moved for approval; LeAnna Kavanaugh seconded and the motion passed by roll call vote with all in favor.
Council did not provide a line-item breakdown during the meeting. Public Works Director Matt Gilles previously reported the Madison Street project is ahead of schedule. The approved pay request represents a substantial construction payment for a capital street project; the council did not specify whether the amount is covered entirely by the city budget, grant funds, or other sources during the meeting.