Pipeline and plant work progressing; South Hillsborough pipeline ~5% complete

Tampa Bay Water Board of Directors · July 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project staff reported the South Hillsborough pipeline is about 5% complete (by linear feet installed) with spending aligned at ~20% of a $478.4M construction budget; the surface water treatment plant expansion is about 6% complete with spending at ~17% of its $167M budget.

Project staff updated the board on construction status for two major projects. Danielle Kersey, senior project manager, said the 26-mile South Hillsborough pipeline route from Brandon to Lithia and Balm is active at multiple work zones, with tunneling already completed at several shafts. "Construction is about 5% complete based on linear feet of pipe installed, and spending is aligned at 20% of the total $478,400,000 construction budget," Kersey reported.

Kersey also briefed the board on the surface water treatment plant expansion: the project will add up to 12.5 MGD of capacity and is currently about 6% complete with spending at about 17% of the $167 million budget. She detailed recent deliveries and installed components (including belt filter presses and ductile-iron piping) and described ongoing public engagement and coordination with Hillsborough County schools, TECO and other utilities to minimize disruptions. Board members asked how stakeholder complaints are logged; Michelle Robinson of Dialogue Public Relations explained the agency uses a database called Simply Stakeholders that logs inquiries and assigns follow-up.