Summary

The authority authorized payments totaling $177,413.82 to KBC Construction and Utility Supply Co. for WWTP construction work; the items were listed as paid from an OWRB loan.

The Bristow Municipal Authority on May 5 authorized payments for work on the wastewater treatment plant that were listed as being paid from an OWRB loan.

Claims approved include #20903 to KBC Construction, Inc. for $166,296.52, #20904 to Utility Supply Co. for $5,120.00 and #20905 to Utility Supply Co. for $5,997.30, for a combined total of $177,413.82. The items were included in the consent agenda and passed on a unanimous roll-call vote of members present.

The meeting record notes the WWTP construction payments specifically as paid from an OWRB loan; no further discussion or conditions were recorded during the consent-agenda vote.