CPUA accepts REAP sewer lamphole project and approves final payments

Carney Public Utilities Authority (CPUA) Board of Trustees · December 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board accepted completion of CA-25-01 (OWRB REAP Sewer Lamphole Replacement Project) and approved final payments: $22,423.90 to RGB3 LLC (with $19,224.90 from REAP and $3,199.00 from CPUA) and $1,072.98 to Infrastructure Solutions Group, LLC.

The Carney Public Utilities Authority accepted project CA-25-01 (OWRB REAP Sewer Lamphole Replacement Project) as complete and approved final payments related to the work. The board approved Pay Application No. 3 (Final) to RGB3 LLC for $22,423.90; the minutes specify that $19,224.90 will be paid from REAP funds with $3,199.00 charged to CPUA.

Separately, the board approved Invoice CA-25-01-04-Final from Infrastructure Solutions Group, LLC for $1,072.98. Both approvals were unanimous and were recorded with motions and seconds (Pay Application moved by Jason Hubach, second by Lynn Hughes; the Infrastructure Solutions invoice moved by Lynn Hughes, second by Joe Simon).