Public works proposes four-tier lane-closure permit system with per-lane, per-day fees to limit long-running downtown closures
Summary
Brent Johnson, director of public works, recommended a four-tier lane-closure permitting system that includes traffic-control plans, renewal periods and a per-lane-per-day fee to incentivize contractors to shorten closures; staff proposed private projects require permits and city projects would be exempt.
Get email alerts on the Lane Closure Policy topic
No spam. Unsubscribe anytime.
Brent Johnson, the city’s director of public works, presented a lane-closure permitting proposal that would require private contractors and utilities to apply for permits, submit traffic-control plans and pay a per-lane-per-day fee scaled by street classification. “Our recommendation would be the level 4 permit system,” Johnson said, describing the most comprehensive tier that includes a permit, a traffic-control plan, a schedule and a daily cost for closures.
Johnson told commissioners that permit review could be handled in-house by the city’s right-of-way program and recommended permit renewals every 60 days to maintain leverage if contractors do not meet schedule commitments. He suggested per-lane fees to encourage faster completion and preserve travelways; staff provided sample rates and said fees could be adjusted by whether the closure is on a local, collector or arterial street. Commissioners asked about grandfathering existing projects, posting of closure schedules and enforcement; staff proposed a short grandfather period (90–180 days) and committed to posting weekly closure lists publicly and on social media. The commission supported pursuing a policy and asked staff to return with ordinance language and recommended fee levels.