Council approves $9,347.68 change order for stormwater work on ENG1148

Statesboro City Council · July 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a $9,347.68 change order with Tim Lanier Construction for additional stormwater-related work on project ENG1148, citing field discoveries and the need for minor additional work.

The Statesboro City Council approved a change order with Tim Lanier Construction in the amount of $9,347.68 for additional work on project ENG1148. Staff explained the change order resulted from conditions discovered after work began in the field, described the work as related to an inlet and stormwater items, and recommended approval.

A staff member said that "once we get into the field, we discover things, and so that's why we have this change order," and described the item as a relatively small, field-driven cost. Council moved, seconded and recorded an affirmative vote on the change order.

Staff said the change order will be funded from the project budget (drive-funded by 2013 funds as read into the record) and that the work addresses stormwater-related adjustments encountered during construction.