Engineer: TAP sidewalk estimate $1.5M; council to narrow scope and hold workshop

Monett City Council · July 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff told council TAP sidewalk plans are submitted to MoDOT and FHWA; sidewalk-only estimate is roughly $1.5M (project total ~$6.18M). Council directed staff to prepare alternates, prioritize worst segments and hold an August workshop to firm scope and budget match.

City engineer Kevin Sprinkle reported that the TAP sidewalk project plans have been submitted to MoDOT and the Federal Highway Administration and that the current sidewalk-only estimate is about $1,500,000; the overall submitted project was roughly $6.18 million.

"The most current estimate on the sidewalks is $1,500,000," Kevin said, adding the bids must come in closer to budget to stay within local-match limits (80% federal / 20% local). Councilors discussed options to reduce scope—prioritizing the worst sidewalks first, using local crews for some work, and including alternates in bid documents so the council can select which segments to fund if bids exceed estimates. Staff said a focused workshop in August would present pick-list alternates for council direction.