Commission approves owner–architect agreement for Point project; staff says GMP set at $10 million with donor pledges covering initial funds
Summary
City approved the owner–architect agreement and accepted a donor pledge agreement for the Point project; staff and the general contractor cited a guaranteed maximum price (GMP) of $10,000,000 with scope alternates that could raise totals toward previously estimated $12.5M.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Commissioners approved the owner–architect AIA contract for the Point project and accepted a donor pledge agreement that formalizes $5.5 million in pledged private funds and a $2.6 million grant from the Kansas Department of Wildlife and Parks. Staff and the architect clarified that the contract’s fee is 3% of a $10,000,000 probable cost and that the General Contractor provided preliminary bids supporting a $10,000,000 guaranteed maximum price (GMP).
City Attorney and staff explained that the GMP protects the city from cost overruns beyond $10,000,000 unless the commission later authorizes add-ons or alternates; donors and staff said additional amenities could push the overall project toward earlier $12.5 million estimates if the commission chooses to add them later. "We have $5,500,000 in pledged funds. We also have a $2,600,000 grant from Wildlife and Parks," staff said, summarizing the funding package. The commission approved the agreements and asked staff to bring contractor documents for subsequent approval.