Planning commission recommends PacifiCorp 178 MW solar and battery project to county commissioners

Emery County Planning and Zoning Commission · August 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

PacifiCorp presented a combined 178 MW solar photovoltaic and battery energy storage project sited on company-owned lands; the Emery County Planning Commission voted unanimously to recommend approval under current level-2 conditional-use rules and will forward the matter to the county commissioners.

PacifiCorp representatives presented a proposed 178-megawatt solar photovoltaic facility paired with a battery-energy-storage system and asked the Emery County Planning Commission to recommend the conditional-use permit to the county commissioners.

Spencer Martin, the consultant who prepared the CUP application, summarized the proposal: "The project is proposing a 178 megawatt capacity solar photovoltaic power generation and battery energy storage system project," spanning roughly 1,170 acres of footprint on mostly company-owned land a few miles south of Castle Dale along State Route 10, with a gen-tie of about 2.9 miles to connect to the grid. Project representatives said construction could start in 2027 with completion in 2028.

Commissioners discussed permitting levels for large solar projects; planning staff warned commissioners that the county could move future large projects to a higher-level (level 3) permit process, which would trigger additional review steps. After discussion, a commissioner moved to recommend approval under current level-2 rules and the body voted unanimously to forward a positive recommendation to the county commissioners. Chair Gary Errington said the county commissioners will have the final say and could elevate the permit to level 3 if they choose.