District says HVAC projects largely complete; targeted fixes being tested at Salt Brook
Summary
School Business Administrator James Testa reported punch lists are in progress, AMCO has started high-school gym and Salt Brook DOAS work, and a communications fix is being tested at Salt Brook with district-wide rollout planned if successful. He said he is "99% sure" work will finish before the end of summer.
Get email alerts on the Facilities Hvac topic
No spam. Unsubscribe anytime.
At the New Providence Board of Education meeting on June 25, School Business Administrator James Testa reported substantial progress on HVAC systems and related projects across the district.
Testa said most HVAC systems are functioning and that contractors H&S have received punch lists they expect to complete by the end of summer. A communication-system fix is currently being trialed at Salt Brook School; if the test continues to perform, the district will roll the solution out to the high school, then the middle school, and finally the elementary schools. "I am 99% sure that we will be done before the end of the summer," Testa told the Board.
AMCO, the contractor for the high school gym HVAC and the Salt Brook DOAS unit, began site work immediately after graduation; materials are ordered and delivery is expected on schedule. Testa said classroom temperature controls will allow teachers to raise or lower temperatures by two degrees; larger adjustments would require a request to the maintenance foreman. The District plans a meeting with all contractors, the business administrator and the superintendent to ensure on-time completion and resolution of remaining communications issues.
The Board did not approve additional funds at the meeting; Testa said current work is on schedule. The Board asked no further questions during the update.