Board approves up to $15,000 change order for irrigation wiring and head adjustments

River Ridge Community Development District Board of Supervisors · November 19, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District Engineer Charlie Krebs presented ancillary costs from Irrigation Concepts to repair damaged wiring ($4,002.50) and raise seven to eight irrigation heads (~$1,300 each). The board approved a not-to-exceed $15,000 change order to cover the work.

District Engineer Charlie Krebs told the board that the revised Seaside & Master Drainage Project scope would make future changes easier and that ancillary irrigation work was required. Krebs presented an itemized estimate from Irrigation Concepts: $4,002.50 to repair damaged wiring and roughly $1,300 each to raise seven to eight irrigation heads.

On motion by Mr. Blumenthal and seconded by Mr. Schultz, and with all in favor, the board approved the Irrigation Concepts change order to repair damaged wiring and raise seven to eight irrigation heads in a not‑to‑exceed amount of $15,000. MRI expected the drainage work to commence within two to three weeks.