Argo council reviews $49,072 paving option and change-order documentation for storm drainage project
Summary
Council discussed adding the Massey Asphalt Paving Proposal (Argo Storm Drainage Project, Option 2, $49,072.00) to the June 8 agenda after unsuitable soil conditions were found; council noted the cost exceeds the 10% change-order threshold and supporting documentation is required.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
During a June 8 work session, the Argo City Council reviewed the Massey Asphalt Paving Proposal for the Argo Storm Drainage Project and discussed adding the item to the June 8 regular meeting agenda. City minutes state that unsuitable soil conditions were encountered during construction and that Option 2, priced at $49,072.00, was recommended.
Council members noted the recommended amount exceeds the municipality's 10% change-order threshold and discussed the need for a formal change order and supporting documentation before final approval. The work session minutes record the item for placement on the regular meeting agenda but do not record a formal vote or final action.