Laurel Bay pathway change order finalizes project; county expects potential utility reimbursements
Summary
A final change order of about $128,167.12 was approved to close out the Laurel Bay Road Pathway project; staff said costs stemmed from Hurricane Debbie impacts, utility relocation, and bond extensions and that some reimbursement from utilities may still arrive.
Get email alerts on the Construction Closeout topic
No spam. Unsubscribe anytime.
Staff presented a final change order for the Laurel Bay Road Pathway project to close out construction and financial accounting. Jared said the project is substantially complete and the change order covers impacts from Hurricane Debbie, utility relocation costs and bond time extensions; the committee approved the change order and staff noted there may be utility reimbursements that reduce net cost.
Jared described the change order as a final balancing action to achieve a zero‑sum closeout for the contract so the county can close the purchase order and finalize financials. Committee members thanked staff and county administration for rapid post‑construction responses to outstanding maintenance items and approved moving the item forward without objection.