Highway crew details culvert work, planned paving and recommends boring test before major repairs

Braintree Select Board · October 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Highway staff reported culvert work at Fairbrook and Flint, confirmed paving of some paved sections in mid‑October, and recommended a $2,500 bore test to check for ledge before committing to a larger culvert repair project estimated at hundreds of thousands of dollars.

Highway staff reported routine and project work, including culvert replacements, ditching and planned paving dates, and recommended a geotechnical bore test before large repairs to limit cost overruns.

The highway foreman (speaker 1) said crews reditched Walker Road and will place new blacktop on scheduled sections Oct. 16–17. For a larger Fairbrook culvert project, staff discussed contractor options (a sub with an excavator/truck), equipment needs and a possible total project cost in the low hundreds of thousands if the town acts as the contractor. To reduce financial risk, staff recommended spending about $2,500 for exploratory borings to confirm whether ledge exists at the site before committing to full construction: "I think the last time I had somebody good mark, there's 2,500," the foreman said.

Board members discussed joint decisions about purchasing an excavator hammer versus continuing to rent that equipment and asked staff to proceed with boring and to return with cost estimates and funding plans (including potential Better Backroads and FEMA reimbursements).