CIP update: 49th Street paving delayed by equipment failure; staff to follow up on access notices

Merriam City Council · December 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Director Kumpke briefed the council on the December CIP packet, highlighting the 49th Street paving project was interrupted by paver breakdowns and that crews will return to finish sidewalks and driveways. Council members raised concerns about access around the I‑35 interchange and neighborhood communications; staff said they would follow up.

Director Kumpke presented the December capital-improvement program update and focused on the 49th Street project, explaining that paving started before Thanksgiving but a paver failure left intersections incomplete; crews are scheduled to return to finish paving and sidewalks.

"They paved before Thanksgiving, and their paver broke down, so they didn't quite finish some of the intersections," Director Kumpke said, and added crews would be back when conditions allowed. Council members pressed for clarity about access at the I‑35 interchange and noted that some neighborhood residents reported closures and difficulty reaching properties; staff said they had issued communications and would follow up on targeted outreach and staging of equipment to preserve access.

Kumpke also reported work on sidewalks from Knox to Antioch and remaining driveway work; council members thanked staff for snow removal and other ongoing maintenance efforts.