Johnson Drive: bids opened, KDOT approval pending; staff says paving aimed for this fall

Mission City Council work session · April 27, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff told council the Johnson Drive reconstruction is in contracting stages: bids open April 10, the project awaits KDOT approval tied to federal funding, and the goal is to finish paving by this fall if approvals and contracts proceed.

Council members asked for an update on Johnson Drive and staff described the near‑term procurement and utility coordination steps.

The Staff member (S2) said, "We open bids on April 10 for the actual GC for the street project... we're waiting on KDOT to give us the approval. We will call a special meeting at whatever point that happens so we can give notice to proceed to the contractor." S2 added the target is to have the street paved before winter, noting remaining lead times for storm structures and traffic signal work.

Presenters (S4,S5) said earlier utility work and staged repairs have made the roadway look patchy while utilities complete their work. Council members asked whether utilities coordinate and staff replied that utility agencies receive the city’s five‑year CIP so they can plan around reconstruction schedules, though sometimes utilities accelerate work at higher cost to meet timelines.