Council reviews 2027–2031 CARS five‑year plan, lists candidate streets and cost estimates

City of Mission — Committee meetings (Community Development; Finance & Administration) · May 7, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff outlined Mission's proposed CARS (County Assistance Road System) five‑year plan with candidate projects including Knoll Avenue ($943,483 est.; Mission share $589,739), Martway Street segments (full reconstruction and mill/overlay), Foxridge maintenance projects, and 51st Street reconstruction; final funding depends on county interlocal agreements and design costs.

City staff presented the required five‑year CARS plan the city will submit to Johnson County for project selection and funding. Stephanie Boyse explained CARS funds typically cover up to half of construction and inspection costs and that Mission’s proposed 2027 project list includes Knoll Avenue (67th to Martway) with an estimated total of $943,483 and a Mission contribution of $589,739, and later Martway Street segments and a potential Johnson Drive/Ash Drive signal replacement project. “This is a joint project with Prairie Village,” Boyse said of Knoll Avenue, noting interlocal coordination and that final funding commitments require subsequent interlocal agreements.

Boyse said some 2030 and 2031 projects are placeholders for budgeting and design, and details will be refined as designs are completed and the council updates the comprehensive street maintenance program. She emphasized the county must still adopt its CIP before final construction funding is committed, and that the city’s approval of the resolution does not obligate Mission to immediate expenditures.