Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Public Works topic

No spam. Unsubscribe anytime.

Parma updates: 5th & 6th Street water work, airport main, kennel and ITD resurfacing

City of Parma City Council · April 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works Supervisor Dustin Riggs reported the 5th & 6th Street water main and service‑line replacements are underway, a 1,200‑foot airport water main was completed, a major leak was repaired near 5th and 7th, work began on a new police dog kennel, and ITD will seal coat Grove and resurface nearby highway in June–July.

Public Works Supervisor Dustin Riggs told the council the 5th & 6th Street water project has started; crews are replacing water mains and service lines and signs are posted around town. He also said a 1,200‑foot water main run to the airport is finished and a large leak near 5th and 7th streets was repaired.

Riggs reported the city has started work on a new dog kennel at the police station and intends to tear down the old kennel and its building at the former police station. He said the Idaho Transportation Department will apply a seal coat to Grove and plans to resurface the highway between Parma and nearby cities in June or July; staff will raise questions about timing and local impacts at the April 29 meeting.

Provenance: topicintro SEG 013, topfinish SEG 014.