Board reviews feasibility study and debates two-proposition bond; tables final language pending Jones Foundation decision
Summary
A feasibility study presented two bond propositions: $18.5M for middle school renovations (Proposition 1) and $12.15M for an early childhood center (Proposition 2). Draft language ties Proposition 2 to Proposition 1; board agreed to table final ballot language until potential Jones Foundation funding is confirmed.
Get email alerts on the Bond Election topic
No spam. Unsubscribe anytime.
Consultants and district staff presented a feasibility study to the Osage City USD 420 board on July 8 that outlined two proposed bond propositions and associated cost estimates.
The study described Proposition 1: middle school renovations including ag/CTE space, fitness/weight/multipurpose areas and site work, estimated at $18,500,000; and Proposition 2: an early childhood center with district administration space, community daycare and outdoor learning, estimated at $12,150,000. The draft ballot language in the packet conditions Proposition 2 on passage of Proposition 1 (Proposition 2 would only be authorized if Proposition 1 passes).
Board members debated whether to tie the two propositions. Several members argued the middle school should be the priority for immediate student-pathway benefits and expressed caution about placing both questions in a linked format. Others said voters should be able to vote separately. A key consideration was possible supplemental funding from the Jones Foundation; several trustees recommended waiting to learn the foundation's decision before finalizing ballot language.
The board did not adopt final bond language at the July 8 meeting. The superintendent said staff will not submit final election documents until after the board decides how to present the propositions; staff noted an administrative deadline in August for ballot materials if the board seeks a November vote.
Next steps: district staff will contact bond counsel and the Jones Foundation and call a special meeting if needed before the submission deadline.