Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Construction topic

No spam. Unsubscribe anytime.

Architect Don says FRC construction progressing; change orders net a credit

Fort Bragg Unified School District Board of Trustees · September 14, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Don, the architect on the Fort Bragg construction project, reported foundation and framing milestones, a schedule delay after a soils-report error, but no net district financial impact; change-order credits produced a reported net credit (~$363,000).

Don, the construction presenter, told the board the building’s foundation has been poured and framing has begun, and he outlined a short schedule impact after a soils‑report issue required rework. He said the architect and geotechnical engineer absorbed costs for the second soils report so the district did not incur extra expense.

"We're talking about credits for what we didn't spend the money on," Don said, describing change orders that reduced rather than increased the project cost. He added that the net change for the project shows a credit of about $363,000.

Don outlined the project timeline: construction started in June; the cafeteria and lobby were completed to allow school opening; remaining admin-area work is scheduled to finish by December and the TK additions are targeted for early next summer. Trustees asked about noise management at back‑to‑school and commended the contractor for being mindful of construction hours.