Board approves change order to complete high-school stadium lighting project
Summary
Trustees approved a change order on the stadium lighting project after contractor site-access issues raised costs; superintendent said the revised price keeps the district within the originally anticipated equipment range (~$250,000) and allows the work to proceed.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The board approved a change order for the Fort Bragg High School stadium lighting project after staff explained unforeseen site-access needs increased the contractor's labor and equipment costs.
Superintendent said the contractor agreed to absorb some costs because the company did not visit the site during bidding; the revised change order keeps total project spending near the district's earlier equipment quote (staff noted roughly $250,000 for lights without labor). Trustees approved the change order on a voice/roll-call vote to allow the vendor to be paid and work to continue.