Council approves amendment for 4 Lakes Substation upgrade, sets May–June milestones

Cheney City Council · March 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved an amendment to the 4 Lakes Substation construction agreement that updates project milestones with construction/model completion by May 15 and cutover/testing by June 15 and records a city deposit of $187,500 toward the work.

Council approved an amendment to the contract for reliability upgrades at the 4 Lakes Substation.

Staff said the amendment replaces an earlier milestones table: construction completion and model updates are scheduled by May 15, with cutover testing and commissioning by June 15 (dates contingent on normal construction progress). The city's share includes a deposit of $187,500 payable by March 15, staff said.

Council discussion affirmed support for the reliability work; staff and utility partners said the amendment will help avoid extended outages by enabling bypass and maintenance work without losing power to the community.