Commissioners approve Keeler temporary-bridge change order after cost increase

Lincoln County Board of Commissioners · April 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Lincoln County commissioners approved a change order adding 20 feet to the temporary Keeler Bridge, increasing the contract by about $190,000; officials said the move avoided conflict with future construction and expected state emergency reimbursement.

Lincoln County commissioners voted to approve a change order for a temporary Keeler Bridge after staff reported the span needed to be relocated and lengthened. The project’s original temporary bridge was 140 feet at $845,473; moving the site downstream to avoid interference with future construction added roughly 20 feet and an additional cost of about $190,000, which commissioners approved by voice vote.

Commissioners said the relocation was chosen to prevent conflicts with a future construction project and that the county expects to be reimbursed through state emergency funds. "It added an additional 20 ft to the length and increased the cost by just under $200,000," a commissioner said during the meeting. The board recorded the motion, a second, and the vote to proceed with the change order.