Board approves $231,575 pay application and two change orders for water treatment plant

Milford Town Board · July 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Milford staff recommended and the board approved Division A pay application for $231,575.02, Division B payment and two change orders (painting $20,580; roof access ladder $14,646). Officials said the project remains roughly $100,000 under budget overall and retains about $160,000 in contingency.

Project engineer Ryan Baru presented the latest contractor pay applications and recommended payment. “This pay application is in total $231,575.02,” he said, describing work on internals of the water treatment plant and delivery of a new generator to the site.

Council discussed two change orders on Division A: $20,580 for exterior painting and $14,646 for roof access including a fall‑arrest ladder. Baru noted a remaining project contingency of about $160,000 and said Division B is running roughly $100,000 under budget overall. After questions about ladder security and caging, the board moved, seconded and approved the pay application and both change orders.

The board also approved Division B pay application number 9 for $185,266.56 covering finishing work on James Street and several water service restorations. Staff said the contractor will present supplemental quotes for additional work at a future meeting.