Commissioners approve initial jail facility evaluation; consultant warns full project could take years and cost much more

Lincoln County Board of Commissioners · August 6, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After a presentation by consultant Rich Siddens of RS Security, commissioners voted to move ahead with a primary facility evaluation (initial assessment budget "just under $19,000") to document deficiencies, estimate capacity and support future planning for a new jail or major renovations.

The Lincoln County Board of Commissioners voted Aug. 6 to proceed with an initial facility evaluation of the county jail after a presentation by consultant Rich Siddens of RS Security. Siddens described a three‑phase approach: (1) a facility evaluation comparing the existing building to state and national standards and identifying code, liability and ADA deficiencies; (2) planning and programming that includes population projections and space requirements; and (3) master planning and site selection with cost estimates. "I'm Rich Siddens. I own RS Security," he said, outlining experience with similar projects and explaining that an initial assessment would produce an operational capacity and a prioritized list of deficiencies.

Siddens provided a rough order‑of‑magnitude planning note and estimated the initial assessment budget at "just under $19,000." He cautioned that a full replacement or large expansion could be years away: even if the county started immediately, he said program definition, design and construction could take seven to 10 years. Commissioners noted prior studies and a recent peer review but said up‑to‑date documentation is important for public outreach and any bond campaign. A motion to move forward with the facility evaluation was made and seconded; commissioners approved using available PILT funds to pay for the initial assessment and asked staff to provide the existing plans and prior reports to the consultant.