Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Utilities topic

No spam. Unsubscribe anytime.

Staff reports Westside Pump Station making progress; wet well precast and pressure tests passed

Sisters Advisory Board · December 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public works staff said the Westside Pump Station force main has been tested and passed, the wet well is precast in three sections totaling about 60,000 pounds, and the project remains on budget with a short punch list remaining.

Public Works staff updated the board on several utility projects, focusing on the Westside Pump Station. "We made it through the bulk of the ripping and tearing of town...That line's been tested and passed, the pressure tests on that," Paul said, noting the wet well is being precast and will arrive in three sections totaling about 60,000 pounds and requiring a large crane for installation. Staff described ongoing inspections (third-party geotechnical and concrete inspectors) and a remaining punch list before final acceptance.

Staff also reported progress on the Edgerton Transmission Main (design contract underway) and said the Forest Service issued a notice to proceed after NEPA analysis covering both the Edgerton line and reservoir improvements. Staff said the pump-station project has remained on budget and that they will continue to monitor weather and sequencing as the work moves to vertical construction and equipment installation.