CDD approves up to $15,000 for irrigation repairs tied to drainage project

River Ridge Community Development District Board of Supervisors · November 19, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved an Irrigation Concepts change order—repairing wiring and raising seven to eight irrigation heads—authorizing a not-to-exceed amount of $15,000 as part of the Seaside & Master Drainage Project.

District Engineer Charlie Krebs presented a revised scope for the Seaside & Master Drainage Project and said MRI expects work to begin in two to three weeks. Krebs noted ancillary irrigation costs tied to the project: Irrigation Concepts proposed $4,002.50 to repair damaged wiring and $1,300 each to raise about seven to eight irrigation heads.

On a motion by Mr. Blumenthal, seconded by Mr. Schultz, the board approved the Irrigation Concepts change order to repair damaged wiring and raise the irrigation heads, authorizing a not‑to‑exceed amount of $15,000. The work is intended to preserve the original drainage project intent while allowing operational adjustments.