Premier Lakes reports minimal red algae, schedules aeration fixes and equipment installation
Summary
Premier Lakes told the board crews found minimal red algae (treatment scheduled), corrected most aeration issues pending electrical work for two units, and will install a 'zombie box' at the Masters in three weeks; staff will obtain littoral replanting cost estimates for 20859 Glen Eagles Lakes Drive.
Get email alerts on the Lake Management topic
No spam. Unsubscribe anytime.
Dustin Hormann of Premier Lakes reported to the River Ridge Board that crews identified minimal red algae in the lakes and planned treatment for the following day. He said dry retention areas were recently treated and that aeration issues were corrected except for two aerators that require electrical work scheduled for next week. Hormann also said a 'zombie box' unit is on back order and will be installed at the Masters in about three weeks.
Eric Long told the Board he had emailed District Engineer Charlie Krebs about inspecting the littorals behind 20859 Glen Eagles Lakes Drive; Krebs will obtain costs to replant cord grass and arrowhead. The board did not take additional action beyond directing staff to obtain cost estimates and schedule necessary electrical work for the remaining aerators.