Trout Pond spillway erosion spurs engineering study; town asked to sponsor grant for repairs
Summary
Trout Pond’s spillway has erosion damage that prevents fish stocking; the Trout Club engaged Dubois & King for engineering (roughly $10,000 in engineering costs) and requested a municipal fiscal‑sponsor route so grant funds from VT Community Foundation or Two Rivers can be accessed.
Get email alerts on the Trout Pond topic
No spam. Unsubscribe anytime.
Brice Blaisdell briefed the Selectboard on Trout Pond, describing it as a 12‑acre parcel with a roughly 7–8‑acre pond and a man‑made dam. He said Vermont ANR has classified the dam as low risk but that the spillway has sustained erosion that currently prevents stocking trout and requires emergency stabilization measures.
Blaisdell said the Trout Club has engaged Dubois & King for an engineering study and estimated engineering costs around $10,000 (not including construction). Because the Trout Club is organized as a for‑profit corporation, Blaisdell said it cannot directly access many grant programs and asked whether the town could act as a municipal fiscal sponsor or whether a nonprofit sponsor could pass funds through. The Selectboard asked staff to obtain a PDF of the Fiscal Sponsor Agreement and to consult Two Rivers about potential sponsorship; no funding commitment was made at the meeting.