Public Works updates: SCADA security, potential generator reuse, and Linn Valley water connection progress
Summary
Public Works Director Dan Nasalroad briefed the council on water plant SCADA security ($400 annual license), proposed reusing a Park Lift Station generator for the community building pending transfer-switch costs, and said pumps for the Linn Valley booster station have arrived with pressure testing expected late December.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Public Works Director Dan Nasalroad updated the council on several infrastructure items. He said the water plant's SCADA security certification was expiring and MicroComm offered a replacement security program that carries a $400 annual license; the new program was scheduled for installation later in the week. Nasalroad also described an option to repurpose the Park Lift Station generator for the community building and said it "is still in decent shape and would be capable of providing all the necessary power" while detailing that staff will further evaluate pad and transfer-switch costs.
On the City of Linn Valley connection, Nasalroad reported pumps for the booster station have arrived and are being installed; he anticipated the main line would be filled, pressure tested and flushed near the end of December 2025. The council did not vote on these items at the meeting; they were given as operational updates and staff committed to follow-up on transfer-switch costs and generator pad installation.