District reports progress on maintenance: middle school roof done; LHS vestibule painting nearly finished; HVAC turnover set for Sept. 17

La Grande School District No. 1 Board of Directors · September 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facilities manager Brad Sunderman told the board the middle school roof project is complete, LHS vestibule painting is ~90% complete, new cameras and LED lights are installed, and HVAC turnover to the district is scheduled for Sept. 17, 2025.

Brad Sunderman reported to the board that several maintenance and capital projects are either complete or near completion. He said the Middle School roof is finished, the LHS vestibule painting is about 90% complete, and the HVAC system will be turned over to the district on Sept. 17, 2025 under the new building management system.

Sunderman also listed completed items including new cameras at Greenwood, Willow, LMS and LHS, new LED main-court lights at LHS, a new high-efficiency domestic water heater at Island City, replaced entry flooring at Island City, Greenwood kitchen upgrades, and an underground sprinkler system at the LHS track. Upcoming projects noted included fencing at Central and Island City, additional irrigation, and updated roller-door sheds for sports storage at LHS.