County approves pay application for government center parking garage; podium work to continue

Kenton County Fiscal Court · January 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Fiscal Court approved pay application #21 to Dugan and Meyers for the Kenton County Government Center parking garage and heard Public Works updates on snow response and transportation-plan kickoff.

The Kenton County Fiscal Court approved pay application #21 to contractor Dugan and Meyers for work on the Kenton County Government Center parking garage during the Jan. 13 meeting. County Administrator Joe Shriver said the payment had been vetted and was appropriate, but noted it was not the final payment for the overall project as podium work and framing continue into spring.

Shriver added that Dugan and Meyers are currently pouring concrete on the first deck along Main Street and that work on the MLK side foundation should be complete in about two weeks. Public Works Director Spencer Stork briefed the court on recent snow-and-ice responses (salt dome restocked) and said the Transportation Plan update kickoff met this week.

Next steps: Pay application processed; construction continues into spring. County staff will continue to update the court on project milestones.