Selectboard approves $76,201 change order and grant amendments for Holmes Meadow floodplain project

Johnson Selectboard · March 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Johnson Selectboard authorized contract and grant amendments that will allow change order No. 4 — $76,201.20 for additional gravel extraction, hauling and related services — to proceed alongside LCPC and BEM grant amendments that fund the work.

The Johnson Selectboard on March 19 approved a set of linked actions to move a Holmes Meadow floodplain restoration project forward: an amendment to the LCPC project‑management agreement, an amendment to the Vermont Emergency Management (BEM) grant agreement, and Change Order No. 4 with Boulder Excavations in the amount of $76,201.20 for additional gravel extraction, loading and hauling.

A committee member presenting the items said the LCPC agreement amendment and the BEM grant amendment were connected to covering the increased cost captured in change order 4. The mover described change order 4 as “for the additional gravel extraction hauling” and stated the board would authorize the chair or town administrator to sign the amendments and change order. Board discussion centered on why per‑cubic‑yard costs rose compared with earlier change orders; one member compared the earlier $7.50 per‑cubic‑yard hauling rate in Change Order No. 1 with the $18.30 per‑cubic‑yard figure in the new order and asked whether differing scope (extraction vs. hauling) explained the variance.

The motions to authorize the LCPC agreement amendment, approve the BEM grant amendment, and execute Change Order No. 4 carried with the board voting in favor. Members asked staff to continue reconciling earlier change‑order language and to track grant reimbursements so town exposure remains limited.