Summary

The board approved a guaranteed-maximum-price addendum with Strickland Construction for the Eagle Lake Roads and Drainage Maintenance Facility, not to exceed $6,381,337.57, with a total construction time of 395 calendar days.

County Manager Bill Beasley asked the board to approve a construction-manager-at-risk guaranteed maximum price addendum with Strickland Construction for the Eagle Lake Roads and Drainage Maintenance Facility, not to exceed $6,381,337.57.

Beasley summarized the project scope: a roughly 3,900-square-foot office building, a 5,400-square-foot maintenance building, a 7,600-square-foot vehicle storage building, and a 5,000-square-foot equipment storage building plus site development and supporting infrastructure. He said the project is included in the board's adopted community investment program and that funding is budgeted in the transportation millage fund; total construction time is set at 395 calendar days.

A motion to approve the GMP addendum was made and carried by voice vote with no opposition. The manager noted prior steps included a master service agreement and preconstruction services totaling $37,818.05.