Warden says roof work near complete, kitchen renovation to be bid June 18 and security checkpoint replaced
Summary
Warden Barnes reported roof recoding at about 90% completion, HVAC replacements nearly done except for the kitchen tie‑in, the kitchen renovation is projected to be advertised for bid June 18, and the security checkpoint building is scheduled to begin in mid‑June.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Warden Barnes updated the board on capital projects at George W. Hill: roof recoding is roughly 90% complete and housing‑unit recoding is advancing with three units finished and a fourth expected in early July. HVAC work is largely complete apart from a kitchen tie‑in awaiting the kitchen renovation schedule.
Barnes said the kitchen renovation project construction documents and cost estimate were being finalized and the county expected to advertise the work for bid on June 18. He also reported that the security checkpoint building at the Cheney Road entrance is being replaced and that initial on‑site construction coordination has taken place with a tentative mid‑June start. Board members praised on‑site coordination and county labor but asked for continued project updates as work proceeds in an active correctional environment.