Water-team flags sodium hypochlorite cell replacement and Hammond waterline progress

Warrenton City Commission · April 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public-works staff briefed the commission on planned sodium hypochlorite cell replacement, a raw-water upstream pipe replacement (RP2) out for bids, and progress toward Hammond waterline phase 1 design-to-bid; staff said selling water currently provides revenue but longer-term supply choices remain.

Public-works/water presenter (speaker 8) described several water projects in the CIP: replacement of the sodium hypochlorite electrochemical cell used for disinfection at the water-treatment plant; an upstream raw-water pipe replacement (RP2) currently out for bids and expected cost returns soon; and the Hammond waterline phase 1, which is moving into the design and potential construction sequence. When asked, staff said the raw-water sales currently provide helpful revenue but that long-term supply planning could change priorities.

Commissioners asked whether the sodium hypochlorite unit is basically a chlorine system (staff confirmed it is the disinfection unit) and whether the RP2 work has begun; staff said bids were submitted and construction timing depends on the design and bid results. For Hammond waterline phase 1, staff said design contracts have been approved and the project is closer to construction than in past years.